PCA New Life is actively planning and has obtained funds for our new Church building.
Click on photos below to enlarge
|
|
|
 |
| Floor Plan |
|
|
Status 0 to 30 days - Completion of the well conversion. Start of some site grading. 31 to 60 days - Arrival of the steel building. Pouring of building pad. Completion of rough grading and water lines 61 to 120 days - Erection of steel building. Beginning of interior construction. Finish of site grading and preparation. 121 to 210 days – Completion of interior construction and finish installation. Paving of parking lot and drives. Installation of landscaping and irrigation system. FIRST SUNDAY SERVICE, December 21st, 2008